Page 8
... December 24 , 1963 , the day preceding the holiday , and he worked the full day on December 26 , 1963 , the day following the holiday . The issue as to whether or not claimant met the " compensation paid him by Carrier is credited to ...
... December 24 , 1963 , the day preceding the holiday , and he worked the full day on December 26 , 1963 , the day following the holiday . The issue as to whether or not claimant met the " compensation paid him by Carrier is credited to ...
Page 1
... December 24 , 1963 , claimants reported for work at 8:00 A. M. and worked a full eight ( 8 ) hour shift . On Thursday , December 26 , 1963 , claimants reported at 8:00 A. M. Claimant Grube worked one and one - half ( 12 ) hours and ...
... December 24 , 1963 , claimants reported for work at 8:00 A. M. and worked a full eight ( 8 ) hour shift . On Thursday , December 26 , 1963 , claimants reported at 8:00 A. M. Claimant Grube worked one and one - half ( 12 ) hours and ...
Page 1
... December 25 , 1962 and New Year's Day , January 1 , 1963 , both legally recognized holidays , fell on Tuesday , a work day of the claim- ants ' regular assignment . Carrier compensated the claimants holiday pay for Christmas Day , December ...
... December 25 , 1962 and New Year's Day , January 1 , 1963 , both legally recognized holidays , fell on Tuesday , a work day of the claim- ants ' regular assignment . Carrier compensated the claimants holiday pay for Christmas Day , December ...
Page 2
... December 1 , 1956 as subsequently amended is controlling . POSITION OF EMPLOYES : It is submitted that under the terms of the controlling agreement , particularly article III - holidays of the August 19 , 1960 agreement , reading in ...
... December 1 , 1956 as subsequently amended is controlling . POSITION OF EMPLOYES : It is submitted that under the terms of the controlling agreement , particularly article III - holidays of the August 19 , 1960 agreement , reading in ...
Page 3
... December 14 , 1962 , and will resume operation on Monday , January 7th , 1963. " At the end of the day's work on Friday , December 14th , 1962 , twelve employes , five of whom are the claimants in the instant dispute , were fur- loughed ...
... December 14 , 1962 , and will resume operation on Monday , January 7th , 1963. " At the end of the day's work on Friday , December 14th , 1962 , twelve employes , five of whom are the claimants in the instant dispute , were fur- loughed ...
Other editions - View all
Common terms and phrases
ADJUSTMENT BOARD SECOND AFL-CIO air brake alleged appeal applicable apprentices August August 19 August 21 axles BOARD SECOND DIVISION Brotherhood car inspectors Carman Helper carmen Carrier's Exhibit CARRIER'S STATEMENT Chairman Chattanooga CLAIM OF EMPLOYES claimant coach cleaners Columbia Falls compensation conference controlling agreement craft December December 17 denied Department dismissed Docket duty effective Electrical Workers electricians employes involved February 17 filed Foreman furloughed employes handled hearing holiday pay January June June 21 jurisdiction locomotive Machinist mechanics ment NATIONAL RAILROAD ADJUSTMENT officer one-half operation Organization overtime board paid paragraph perform ployes preceding the holiday qualified R. E. Powers RAILROAD ADJUSTMENT BOARD Railway Company RAILWAY EMPLOYES Railway Labor Act record referred regularly assigned employes reinstatement repair request rule Second Division Award Section September September 22 sheet metal workers STATEMENT OF FACTS submitted SYSTEM FEDERATION Third Division Award tion train violation workday wrecking crew yard